Press brake tonnage calculator — air bend, bottoming and coining

Work out the force a bend actually needs, in kN per metre and in tonnes across your bend length, then check it against your machine capacity and your tooling's rated load. Formula shown, no sign-up.

Tonnage calculator

Single bend, full length in one hit. Updates as you type.

F (kN per metre) = 1.42 · Rm · t² / V
Total kN = F × bend length (m)  |  tonnes = kN / 9.81
Bottoming ≈ 3–5 × air bend force  |  Coining ≈ 10 × or more
rnat ≈ 0.16 · V  |  minimum flange ≈ 0.65 · V + t

Rm is tensile strength in N/mm². 1.42 is the constant published by most tooling makers for air bending; expect real-world agreement within roughly 10–15%. Bottoming and coining multipliers are rough approximations — they move with punch radius, die angle and how hard the machine is set to press.

Force required
tonnes
ResultValue
Force per metre
Total force
Machine load
Tooling load
Inside radius (air bend)
Minimum flange

Guidance only. Check the rating stamped on your tooling and the load limits in your machine manual before bending. Full disclaimer.

Need the flat pattern too? Bend allowance calculator →

Tonnage reference table — mild steel, per metre of bend

Rm 410 N/mm², using the usual V-die for each thickness. Generated by the same code as the calculator, so the two can never disagree.

ThicknessV-dieAir bend kN/mAir bend t/mBottoming t/mCoining t/m
1 mmV6979.930–4999+
1.5 mmV1013113.440–67134+
2 mmV1219419.859–99198+
2.5 mmV1622723.270–116232+
3 mmV2223824.373–121243+
4 mmV2635836.5110–183365+
5 mmV3245546.4139–232464+
6 mmV4052453.4160–267534+
8 mmV5074576.0228–380760+
10 mmV6392494.2283–471942+
12 mmV801048106.8320–5341068+

Read across: a 3 mm bend over a V22 die needs about 24 tonnes per metre air bending — but around 73–121 t/m bottoming, which is where tooling and machines get hurt.

How press brake tonnage works

Thickness is squared, so it dominates everything

Force scales with the square of thickness. Going from 3 mm to 6 mm does not double the tonnage — it roughly quadruples it, before you even account for the wider die you would normally move to. This is the single most common reason a job that ran fine yesterday stalls the machine today.

The die opening is your tonnage control

Force is inversely proportional to the V opening. Open the die up and the tonnage drops — but the inside radius grows with it, at roughly 16% of the die opening, and springback increases. That trade-off is the whole craft of die selection: the narrowest die that gives you the radius you want, without exceeding the load your tooling and machine can take.

Air bending, bottoming, coining

Air bending only touches three points — punch tip and two die shoulders — so it needs the least force, and the formula above applies directly. Bottoming presses the material into the die and needs roughly three to five times that force. Coining crushes the material at the bend, effectively removing springback, and needs on the order of ten times or more. Those multipliers are approximations, and they are why a coining job on thick plate can exceed a machine that handles the same bend comfortably in air.

Two limits, not one

The machine's rated tonnage is not the only ceiling. Tooling has its own rated load per metre — commonly in the region of 80 t/m for standard precision-ground sections and higher for heavier styles, but it is printed in the supplier's catalogue and you should use their figure, not a guess. Exceed it and the punch or die fails, not the sheet. Short bends concentrate load badly: 30 tonnes spread over 2 metres is routine, the same 30 tonnes over a 150 mm punch is 200 t/m and will damage tooling. The calculator flags this.

Off-centre and short bends. Loading one end of the bed, or bending short parts away from the centre, puts uneven strain on the frame and cylinders regardless of what the total tonnage figure says. Keep short work centred, and check your manual's load-distribution limits — some machines derate significantly for concentrated loads.

FAQ

How many tonnes to bend 3 mm mild steel?

Air bending over a V22 die, about 24 tonnes per metre of bend — so roughly 60 tonnes for a 2.5 m bend. Bottoming the same bend takes three to five times that. Change the die opening and the answer changes.

Does a stronger material need more tonnage?

Directly proportionally. Force scales linearly with tensile strength, so stainless 304 needs about 45% more force than mild steel of the same thickness, and abrasion-resistant plate can need three times or more. Nominal figures also understate reality — real coils commonly run above their minimum specified strength.

Why does my machine struggle even though the tonnage looks fine?

Usual suspects: the die is narrower than you think, the material is stronger than the nominal grade, you are bottoming rather than air bending, or the load is concentrated over a short length or off-centre. Check those four before assuming the machine has a fault.

Is 1.42 the right constant?

It is the constant most tooling manufacturers publish for air bending, and it is what this page uses. You will also see 1.33 and 1.65 in various references depending on assumptions and units. All of them are empirical — treat the result as an estimate with roughly 10–15% uncertainty, and add margin.

Other calculators

Disclaimer and terms of use

Please read this before using any figure from this page in production.

No warranty. This page and its calculators are provided free of charge, “as is” and “as available”, without any warranty of any kind, express or implied, including without limitation any warranty of accuracy, completeness, fitness for a particular purpose, or non-infringement. The formulas and tables used are published empirical and standards-based approximations. They are not a substitute for the specifications of your machine, tooling or material.

Results are estimates, not engineering approval

Every output here is an indicative calculation produced from the values you enter. Real results vary with springback, grain direction, tooling condition and geometry, friction and lubrication, machine calibration and load distribution, temperature, and batch-to-batch variation in material properties. Actual tensile strength commonly differs from the nominal figures listed. Treat these numbers as a starting point to be proven on a test piece — never as a verified value for a production run, a load calculation, or a safety-critical component.

You remain responsible for your own work

You are solely responsible for confirming that the load, thickness, material and tooling are within the rated capacity of your press brake, punches, dies and any adaptors; for complying with the machine manufacturer's manual and load limits; for complying with all applicable workplace health and safety obligations, standards and regulations in your jurisdiction; and for having any structural, safety-critical or certified work checked and approved by a suitably qualified person. Where a calculation affects safety or structural integrity, it must be independently verified by a competent professional engineer.

Limitation of liability

To the maximum extent permitted by law, the operators of this site accept no liability for any loss, cost, injury, or damage of any kind — whether direct, indirect, incidental, special, consequential or economic, including damage to machinery or tooling, scrapped or reworked material, production downtime, lost profits, or personal injury — arising out of or in connection with the use of, or reliance on, this site, its calculators, its charts, or any content on it, however caused and whether arising in contract, tort (including negligence), statute or otherwise. Nothing in these terms excludes, restricts or modifies any consumer guarantee, right or remedy that cannot lawfully be excluded. Where liability cannot be excluded but may be limited, liability is limited to the resupply of the relevant information, being nil in monetary value as this service is provided free of charge.

No professional relationship

Use of this site does not create any engineering, consulting, advisory, or professional relationship. Nothing here constitutes professional engineering advice, certification or sign-off for any specific part, machine, or application.

Standards and third-party references

References to standards such as DIN 6935, ASTM A1008/A1011 or gauge conventions, and to any machine or tooling manufacturer, are provided for context only. This site is not affiliated with, endorsed by, or a licensed reproduction of any standards body, machine manufacturer or tooling manufacturer. Always work from the current, official text of any standard you must comply with, and from your supplier's own tooling and material data.

Privacy and changes

All calculations run locally in your browser. Nothing you enter is transmitted to or stored by this site, and no account is required. This site may be changed, corrected or withdrawn at any time without notice. If you believe a formula or figure here is wrong, please say so in the comments on the Hard Metal Explained channel — corrections are welcome and will be made.

By using this site you accept these terms. If you do not accept them, do not use the calculators. Last updated 6 August 2026.